Feasibility clearance is the distribution company's (DISCOM's) technical yes or no on connecting a rooftop system to its network. Since 22 February 2024 the national rules deem a complete application up to 10 kW accepted without any study, and above 10 kW the DISCOM has 15 days to finish one. In practice applications still stall, because the portal shows only a stage label and each state adds its own rules.

Take a customer in a Surat colony who signs for a 12 kW system. Your team files the application, the portal shows Application Submission, and nothing moves for three weeks. The customer asks what the DISCOM is doing. You need to know which time limit applies, whether the local transformer has room, and who to call next.

This guide reads the official text for each layer: the national rules, the PM Surya Ghar manuals, and the own-site procedures of MSEDCL (Maharashtra), BESCOM (Karnataka) and the Gujarat regulator. Every figure carries its source, jurisdiction and date. It is a process guide, not legal advice, and where a document is silent we say so.

Key takeaway

Feasibility clearance is the DISCOM's check that the customer's connection and the local transformer can take the system. Under the Electricity (Rights of Consumers) Rules as amended on 22 February 2024, a complete rooftop application up to 10 kW is deemed accepted without a study. Above 10 kW the study must finish in 15 days or the proposal is presumed feasible. Transformer limits, such as 70% in Maharashtra and 80% in Karnataka, still decide partial approvals.

How this was checked: we opened every document cited here on 31 October 2026. The portal itself returned an access-denied page, so portal screens come from MNRE's manuals of June and July 2024 and may have changed. DGVCL's site and the Karnataka regulator's site would not load and Tata Power-DDL's files were blocked, so Gujarat is read through the regulator's gazette and Delhi is left out.

What feasibility clearance checks, and what it leaves for later

The DISCOM checks whether the customer's connection and the local network can carry the capacity you applied for. The documents we read name six things: the load limit, the connection voltage, headroom on the distribution transformer, rooftop capacity already on that transformer, dues on the account and, in Maharashtra, whether the roof has shadow-free area. Our feasibility clearance glossary entry gives the short definition.

What is checkedWhat the official document saysWhere
Sanctioned load or contract demandApplied capacity must not exceed it (MSEDCL: "less than or equal to the sanctioned load/contract demand"). Up to 10 kW the DISCOM raises the load to match.MSEDCL SoP (file dated 4 Apr 2022); Rights of Consumers Rules rule 11(7A), 22 Feb 2024
Connection voltageMERC lists the AC voltage level at which connectivity is sought. BESCOM's guideline sets 230 V up to 5 kWp, 400 V above 5 kWp to 150 kWp and 11 kV above 150 kWp.MERC Regulations 2019, Annexure 1(c); BESCOM guidelines, 5 Aug 2023
Transformer headroomCumulative rooftop capacity on the transformer is compared with a state limit (see below).MERC Reg 5.2; BESCOM guidelines item 23
Rooftop capacity already on that transformerMSEDCL's tool subtracts capacity already sanctioned. Gujarat's report lists solar "already connected as well as approved/sanctioned on this transformer".MSEDCL SoP; GERC Fourth Amendment, 6 Sep 2024
DuesMSEDCL: no arrears at application, or the application is not submitted. Gujarat's report includes a "No dues certificate".MSEDCL SoP; GERC Fourth Amendment, 6 Sep 2024
Roof and siteMSEDCL's field officer can reject if "shadow free area is not available" or the capacity was entered wrongly. BESCOM's form asks for shadow-free area.MSEDCL SoP; BESCOM 1 to 10 kW procedure, Aug 2023

Sources: documents named in the last column, opened 31 October 2026.

Inverter phase, single or three, is the item installers ask about most, and the documents are quiet on it. The portal's installation form has a "Phase of Solar Inverter" drop-down, but none of the documents we read makes phase a separate pass-or-fail test. Ask your sub-division what it checks. Gujarat's report also records the last year's maximum demand.

Feasibility comes before installation. The connection agreement, the meter, any electrical inspector sign-off (see our guide to when you need the Electrical Inspector and the CEI glossary entry) and commissioning usually come after. Gujarat is an exception: its table puts inspector approval of the drawings before the DISCOM application. For the full sequence see the DISCOM approval process guide, and for the filing steps see how to apply for net metering.

The national rule: what changed on 22 February 2024

The Electricity (Rights of Consumers) Amendment Rules, 2024 (G.S.R. 125(E), 22 February 2024) rewrote the feasibility rule for rooftop solar. We read the Gazette text itself, published in the Gazette of India, and the PIB release of 23 February 2024. The numbers below are rule 11 of the principal Rules.

10kW

Complete applications up to this size are deemed accepted without a feasibility study

Source: Rights of Consumers Amendment Rules, G.S.R. 125(E), rule 11(7A), 22 Feb 2024

15days

Study time above 10 kW, after which the proposal is presumed feasible (earlier limit: 20 days)

Source: rule 11(7); PIB, 23 Feb 2024

15days

For the DISCOM to sign the agreement, fit the meter and commission after the installation certificate (earlier: 30)

Source: rule 11(9); PIB, 23 Feb 2024

₹500per day

Minimum compensation to the consumer for DISCOM delay without just cause

Source: Rights of Consumers Rules, 31 Dec 2020, rule 11(12)

Your situationWhat the Rules sayRule
Complete application, up to 10 kWDeemed accepted, no study. The DISCOM does any matching rise in sanctioned load.11(7A)
Above 10 kWStudy completed in 15 days and the result told to the applicant. If not, the proposal is presumed technically feasible.11(7)
Network upgrade needed (service line, transformer capacity)Done by the DISCOM or the consumer, as the case may be. Up to 5 kW, or a higher size set by the State Commission, the cost goes into the DISCOM's revenue requirement.11(8)
After installationConsumer submits the installation certificate. DISCOM signs the agreement, installs the meter and commissions within 15 days. Formats must be on the DISCOM's web portal.11(9), 11(9A)
Application recordAcknowledgement with a registration number; the application is deemed received on that date. Tracking by registration number. A single point of contact and the document list must be displayed.11(5)(b), 11(6)
DelayDISCOM must adhere to the timelines and needs Commission approval to overrun in specific cases. Compensation of at least ₹500 a day for delay without just cause.11(11), 11(12)

Sources: Gazette G.S.R. 125(E), 22 Feb 2024; Gazette G.S.R. 818(E), 31 Dec 2020. The 2021 to 2023 amendments leave these sub-rules unchanged.

Three details decide whether the clock helps you. The Rules define "days" as "clear working days" (Rights of Consumers Rules, 2020, rule 2(g)), unchanged in 2024. The clock runs from the acknowledgement with a registration number, not from the day your rep finished the form. And the deemed rule covers only an application "complete in all respects", so a missing item stops the clock before it starts.

Watch out. Older posts, including some of ours, quote a 20-day feasibility limit and a 30-day commissioning limit. Those were the 2020 figures. The Ministry of Power also issued draft Rights of Consumers Amendment Rules, 2026 for comment on 12 March 2026, as listed in MNRE's March 2026 policy update. We found no notified final version, and MNRE's September 2026 update lists none. Until you see a Gazette notification, treat the 2024 text as the current national rule.

What "deemed" does and does not mean

Deemed acceptance removes a study. It does not remove the work around it, and your DISCOM's system may lag the rule.

What deemed acceptance gives you

  • ✓No feasibility study for a complete application up to 10 kW
  • ✓A rule you can quote if a DISCOM asks for a study anyway
  • ✓The DISCOM, not the customer, raises the sanctioned load to match
  • ✓Above 10 kW, 15 days of silence means the proposal is presumed feasible

What it does not do

  • ✗It does not make the DISCOM's own portal show an approval
  • ✗It does not cover an incomplete application
  • ✗It does not skip the agreement, meter and commissioning steps
  • ✗A presumed-feasible proposal can still need a transformer upgrade, and rule 11(8) then decides who does the work

The scheme guideline says the same thing in plain words. MNRE's PM Surya Ghar CFA guidelines, clause 6(h), repeat the 10 kW rule and add: "Till the operationalization of this provision by respective Regulatory Commissions/DISCOMs, the consumer shall upload the necessary documents for seeking feasibility approval, wherever required as per extant state regulations." So the rule exists nationally, but each state and DISCOM has to switch it on in its systems.

The Clock-Cap-Ladder check for an application stuck at feasibility

An application can be stuck for three different reasons, each with a different fix. The Clock-Cap-Ladder check asks about them in order: Clock, then Cap, then Ladder. It takes five minutes per application.

  1. 1

    Clock: which timer applies, and when did it start?

    Work out the route (deemed up to 10 kW, a study above 10 kW, or your state's own table). Take the acknowledgement date as day zero and count clear working days. If the clock has not run out, note the due date and wait. If it has, check the Cap, then climb.

  2. 2

    Cap: is it the clock, or the transformer?

    A slow file and a full transformer look the same from outside. Ask the sub-division: how much rooftop capacity is already sanctioned on this customer's transformer, and what is the limit? If there is no room, waiting does not help (see the Cap list below).

  3. 3

    Ladder: which rung comes next?

    Start at the lowest rung not yet tried (contact, written reminder, portal grievance, grievance forum, Ombudsman, compensation claim) and write down the date and name each time.

Where teams lose weeks is step 2: they chase the clock when the real problem is the cap, or they escalate when the clock has not expired. The three cells (route and due date, headroom answer, rung and date) become columns in the tracking table near the end.

How feasibility shows on the PM Surya Ghar portal

On the national portal, feasibility is stage 3 of ten. In MNRE's installer manual of 29 June 2024, the tracker on each vendor application card reads: 1 Consumer Registered, 2 Application Submission, 3 Feasibility Approval, 4 Vendor Selection, 5 Work Start, 6 Solar Installation Details, 7 Inspection, 8 Project Commissioning, 9 Subsidy Request, 10 Subsidy Disbursal. One screenshot in the same manual labels stage 3 "Feasibility Waived-off" instead. Our vendor login and dashboard guide walks through the whole tracker.

On the application page, the Application Details block shows Sanctioned Load, Proposal Capacity and Existing Installed Capacity. The Installation Details block has "Feasibility Approved by" (the sample reads "Approved with Applied Capacity"), "Applied Capacity", "Lower Capacity" and "Remarks", and the Documents block has a "Feasibility Documents" link. On the consumer side, the master manual of 29 July 2024 shows a downloadable "Feasibility Letter" and a "Track Details" button for "comments received from DisCom".

On the portalWhat the MNRE manual showsWhat it does not tell you
Stage 3 label"Feasibility Approval" in the tracker; "Feasibility Waived-off" in one screenshot (installer manual, 29 Jun 2024)The manual does not define the second label. It fits the deemed rule, but check the letter or ask the DISCOM.
Flow chart box"Technical Feasibility Approval/ Waive-off in 48 DisComs" (master manual, 29 Jul 2024)What "48" counts. The manual does not explain it, so we do not read it as a time limit.
Time limitNo number of days is printed for stage 3 in either manualThe timer comes from your state's regulation, not from the portal.

Sources: MNRE Installer Manual, 29 June 2024; MNRE Master Manual, 29 July 2024. Live portal not accessible to us.

Who owns the timer? The CFA guidelines, clause 13(b), make the DISCOM the State Implementation Agency, which "shall ensure adherence to timelines specified for provisioning of services for prosumers". They do not restate the days. Clause 8(a)(i) says the portal "will be fully integrated" with state DISCOM portals, which reads as a plan. MSEDCL's procedure, for example, describes its own application on its own site, so ask your sub-division whether a second entry is needed.

Fast tip. Before you order material for a job at stage 3, open the application, compare Applied Capacity with Lower Capacity and your design, and read Remarks. If the DISCOM approved less than you quoted, fix the proposal first. Our documents list for the site visit covers what the customer must upload.

Three states, three procedures

The national rule sets the floor, and each State Commission and DISCOM fills in the rest. The table compares three jurisdictions using their own documents. Each cell names its jurisdiction and its document date. Our state guides for MSEDCL, BESCOM and DGVCL give the full application steps, and the DISCOM list covers other states.

Maharashtra (MSEDCL)Karnataka (BESCOM)Gujarat (state DISCOMs, GERC)
Documents and datesMERC Regulations, 2019 (30 Dec 2019); Second Amendment (Maharashtra Gazette, 29 Aug 2024); MSEDCL SoP (file dated 4 Apr 2022)BESCOM guidelines (5 Aug 2023); Common SOP (file dated 17 Oct 2025, date line blank); KERC order of 1 Jun 2023 as quoted by BESCOMGERC Fourth Amendment, Notification 13 of 2024 (Gujarat Gazette, 6 Sep 2024)
Up to 10 kWDeemed accepted, no study (MERC Annexure 1 clause c, substituted 29 Aug 2024). The 2022 SoP predates this.BESCOM's SOP treats everything up to 150 kW as "deemed feasible", with no report. For LT domestic consumers up to 150 kW the work approval is auto-generated after the application is registered.Deemed accepted, no study, same wording as the national rule.
Transformer limit70% of rated capacity; more allowed after a detailed load study (Reg 5.2). MSEDCL's tool: available = 70% of transformer capacity minus capacity already sanctioned.80% of rated capacity for plants below 150 kW. Above 150 kW, the 11 kV feeder current must stay within 80% of its rating.No percentage in the amendment. The field report must say whether total rooftop capacity is "within the rated capacity of transformer". Transformer capacity is updated yearly (Reg 5.1).
Who checks and howField officer visits with the empanelled agency and approves or rejects on a mobile app. Printed reasons: no shadow-free area, wrongly entered capacity. No transformer room: pending or waiting list.Above 150 kW the sub-division visits and the portal generates a report. Below that, no report.Head office asks the circle or division for a report listing feeder, transformer capacity, solar already on it, demand, dues and any estimate.
ClockStudy in 15 days or presumed feasible (2024 amendment). Sanction valid six months (SoP).Above 150 kW: acknowledge in 3 working days, approve or reject in 10 working days (SOP).Letter to field in 3 days, field report in 10 days, consent letter 2 days after the report. Strengthening estimate payable in 30 days.

Sources: documents in the first row. KERC's site would not load, so Karnataka's regulation is read as quoted by BESCOM.

Karnataka goes further than the national floor, deeming applications feasible up to 150 kW, but its documents also state an 80% transformer limit and do not say how that limit is checked on an application that gets no report. Gujarat's table is the most specific on days, and the report content is a ready checklist for what your sub-division must look at.

Worked example: the same transformer in two states

An illustration with assumed numbers, built from two official examples: a 100 kVA transformer with 60 kW of rooftop solar already connected or approved, and a customer who wants 50 kW.

StepMaharashtra (MSEDCL SoP formula)Karnataka (BESCOM guideline, item 26)
Limit on this transformer70% of 100 = 70 (SoP does not state a kVA to kW factor, so we take the figure at face value)80% of 100 kVA = 80 kVA, which BESCOM's own example converts to 68 kW
Room left after the 60 kW70 minus 60 = 10 kW68 minus 60 = 8 kW
What happens to the 50 kW askCannot be sanctioned above 10 kW. Pending or rejected, or the customer sends a consent letter to cut the capacity. Waiting list only if the customer chose it.BESCOM's example: feasible for partial capacity, 8 kW of the 50 kW asked.

Illustrative. Sources: MSEDCL SoP (4 Apr 2022); BESCOM guidelines (5 Aug 2023).

₹ math. A 50 kW system cut to 8 kW is a 42 kW shortfall on the job. At an assumed ₹45,000 per kW installed (an illustrative figure, not a market quote), that is ₹18.9 lakh of project value (42 x ₹45,000) that leaves your order book unless you win a transformer upgrade, a second connection or a customer who agrees to the smaller size.

What to submit so the clock starts

The clock starts only on a complete application, so the file matters more than the follow-up. Every DISCOM must display its "complete list of documents required" (rule 11(5)(b)(iv)), and that list is the final word. Use this as a pre-submission check on top of it.

  1. 1

    Capacity within the sanctioned load

    Check the bill. If the customer wants more, ask how the DISCOM raises the load first. Up to 10 kW the national rule makes the DISCOM do it.

  2. 2

    No dues on the account

    MSEDCL will not accept an application with arrears, and Gujarat's report includes a no-dues certificate. Clear dues before filing.

  3. 3

    Site facts that are true

    Shadow-free area, connection voltage and the right consumer number. MSEDCL's portal fills the transformer code from billing data, so check it against the bill. A wrongly typed capacity is a printed reason for rejection.

  4. 4

    The documents the portal and the DISCOM ask for

    On the national portal the customer uploads an electricity bill, and the guidelines say feasibility documents are needed "wherever required as per extant state regulations". Our site-visit documents list splits portal items from DISCOM items.

  5. 5

    Drawings, where your state asks for them

    Gujarat's table puts Chief Electrical Inspector approval of the single line diagram, earthing diagram and wiring diagram (10 days) before the DISCOM application. Whether a small home system needs it is a question for the DISCOM.

  6. 6

    A consent letter ready for a smaller size

    MSEDCL cuts the applied capacity on a consent letter. A letter signed at the survey saves a round trip if headroom is short.

Keep the acknowledgement slip or screenshot with the registration number. It is the proof of your day zero.

When feasibility is reduced or rejected: the Cap list

A reduced or rejected feasibility is usually a transformer problem, not a paperwork problem. The options below come from the official texts, and the right one depends on your state.

SituationOptionBasis
Headroom is smaller than the askAccept the lower capacity. The portal has a Lower Capacity field, BESCOM sanctions partial capacity, and MSEDCL takes a consent letter to reduce.MNRE installer manual p. 20; BESCOM guidelines item 26; MSEDCL SoP
No headroom at allAsk to stay in the queue. MSEDCL's application has a waiting-list option, a message goes to the sub-division and the applicant when the transformer is augmented, and MERC says applications may be considered in chronological order.MSEDCL SoP; MERC Reg 9.7 (29 Aug 2024)
You need more than the cap allowsIn Maharashtra the DISCOM may allow more than 70% after a detailed load study. Ask for the study in writing.MERC Reg 5.2 proviso
The transformer needs upgradingThe DISCOM or the consumer does the work, and cost for up to 5 kW (or the state's higher size) sits in the DISCOM's revenue requirement. Gujarat fixes 6 kW, and above that the applicant may pay. Maharashtra's Regulation 9.7(a) puts the cost of strengthening for rooftop solar in the DISCOM's annual revenue requirement without a kW limit.Rule 11(8); GERC Reg 5.1 (6 Sep 2024); MERC Reg 9.7(a) (29 Aug 2024)
You doubt the transformer figuresMaharashtra requires DISCOMs to publish transformer-wise capacity on their website every quarter. Gujarat requires a yearly update to the Commission. Ask for the figure for your transformer.MERC Reg 5.3; GERC Reg 5.1
The dispute is about the cap itselfIn Maharashtra the consumer grievance forum may take technical help from an independent advisor empanelled with MEDA.MERC Reg 11.8 proviso

Sources: documents named in the last column.

Watch out. Ask for the reason in writing. The 2019 MERC text said the consumer should be informed in writing, with reasons, when approval fails for transformer capacity. The Regulation 9.7 substituted on 29 Aug 2024 does not repeat that line, and rule 11(7) only says the outcome is "intimated to the applicant". A written reason is what a grievance forum will ask to see.

When feasibility is late: the Ladder

If the clock has run out and the headroom is fine, climb. Each rung below has a basis in the official text. The customer is the consumer in law, so for rungs 4 to 6 get the customer's signed consent to act for them, and check who may file under your state's regulation.

RungWhoBasis
1. Single point of contactThe sub-division's nodal officerDISCOMs must display a single point of contact (rule 11(5)(b)(ii)). BESCOM names the sub-divisional officer as nodal point; MSEDCL names nodal officers at zone and circle level.
2. Written reminderSame office, with a copy to the circleRule 11(7) or 11(7A), plus your state's clock
3. Scheme grievanceNational portal, call centre or portal appCFA guidelines clause 11: resolved within 30 days, tracking ID issued
4. Consumer grievance forumForum at sub-division, division, circle, zone or company levelRights of Consumers Rules rule 15: normally 30 days, not beyond 45
5. OmbudsmanAppointed by the State CommissionElectricity Act, 2003, section 42(6) and rule 15(3)
6. CompensationThe customer's claim against the DISCOMRule 11(12): at least ₹500 a day for delay without just cause. Gujarat repeats it in its 2024 regulation.

Sources: Gazette G.S.R. 818(E) (rules 11 and 15); PM Surya Ghar CFA guidelines; Electricity Act, 2003, section 42(5) to (8). Filing windows and forms are set by each State Commission, so read your state's forum and Ombudsman regulation before rung 4.

The ₹500 rule has a catch: it covers delay "without any just cause", and rule 11(11) lets a DISCOM seek the Commission's approval for an overrun in specific cases. A full transformer is a reason a DISCOM can cite, which is why the Ladder comes after the Cap check.

Fast tip. Put rungs 1 and 2 in writing. A phone call leaves no date, and a forum will ask when the DISCOM was first told. Log every call on the customer's record the same day.

Your feasibility tracking table

Keep one row per application and review every row weekly. The rows below are illustrative: names, dates and sizes are made up, and due dates use the national 15-day rule counted Monday to Friday with no holidays, so recount on your DISCOM's calendar.

Customer and sizeRouteDay zero (acknowledged)Due datePortal stage or DISCOM statusCap answerNext action and dateRung
Customer A, 5 kW (sanctioned 6 kW)Deemed, up to 10 kWMon 3 Aug 2026None, deemed once completeStage 3, Feasibility Waived-offNot askedDownload the letter, confirm it matches 5 kW, Tue 11 AugNone
Customer B, 12 kW (sanctioned 15 kW)Study above 10 kWMon 3 Aug 2026Mon 24 Aug 2026 (15 working days)Stage 2, Application SubmissionNot asked yetAsk sub-division for headroom, Wed 12 Aug1
Customer C, 30 kW (sanctioned 40 kW)Study above 10 kWMon 3 Aug 2026Mon 24 Aug 2026Reduced to 8 kW in letterLimit reached, 8 kW roomConsent letter or waiting list decision, Fri 28 AugNone, Cap list
Customer D, 15 kW (sanctioned 18 kW)Study above 10 kWMon 3 Aug 2026Mon 24 Aug 2026No reply after due dateHeadroom confirmedWritten reminder quoting rule 11(7), Tue 25 Aug2

Illustrative rows. Counting follows rule 2(g) of the Rights of Consumers Rules ('clear working days'); confirm with your DISCOM how it counts the first day and holidays.

Write the due date the day the acknowledgement arrives, record the Cap answer as a number and a date (not "enough"), and name the owner of each row.

How Quickest Solar CRM fits

The portal and your DISCOM's website are the official records. Your CRM is where your own team keeps the promises it made to the customer. Quickest Solar CRM has no link to the national portal or to any DISCOM system, so every status below is typed in by a person, whichever tool you use.

What the pipeline side of Quickest Solar CRM can hold for this work:

  • Pipeline stages you can customise: add stages such as "Feasibility pending", "Feasibility reduced" and "Feasibility cleared" so every application sits in one visible column.
  • Labels and follow-up reminders on the lead: label the route ("Deemed" or "Study") and the due date ("Due 24 Aug"), then set a reminder for your own nudge date.
  • Activity log, also on several leads at once: log each call, letter and reference number on the lead. When a sub-division gives one answer for many customers, log it on all of those leads together, and filter leads by label to build the week's chase list.
  • Team members with permissions, dashboard and team report: the weekly review of stuck applications happens in one place, and each person sees only what you allow.

If you want to see this set up with your own stages, book a demo.

What to do this week

  1. List every application at feasibility. For each one, write the route, the acknowledgement date, the due date and the portal stage or DISCOM status.
  2. Ask each sub-division one Cap question. How much rooftop capacity is already sanctioned on the customer's transformer, and what is the limit? Write down the number, the name and the date.
  3. Send the first written reminder on any application past its due date, quoting rule 11(7) or 11(7A) and your state's clock, and log it with the date.

Frequently asked questions

What is feasibility clearance for rooftop solar?

It is the DISCOM's technical check that the customer's connection and the local network can take the proposed system, looking at sanctioned load, connection voltage and transformer headroom. Under the Electricity (Rights of Consumers) Rules as amended on 22 February 2024, a complete application up to 10 kW is deemed accepted without a study. Above 10 kW the DISCOM has 15 days to finish the study, or the proposal is presumed technically feasible.

Do I need feasibility clearance for a rooftop system up to 10 kW?

Under the national rules, no study is needed for a complete application up to 10 kW. MNRE's scheme guidelines add that until a state regulator or DISCOM puts this into practice, the consumer uploads feasibility documents wherever existing state rules require them. Check what your DISCOM and the portal actually ask for, and quote the Gazette rule if a study is demanded anyway.

How many days does a DISCOM have for feasibility above 10 kW?

Fifteen days, which the Rules define as clear working days, counted from the acknowledgement with a registration number. The earlier limit was 20 days. If the outcome is not told to the applicant in time, the proposal is presumed technically feasible. Your state regulator may set shorter clocks, as Gujarat's 2024 table does for individual steps.

What is the transformer limit for rooftop solar?

It depends on the state. MERC Regulation 5.2 in Maharashtra sets 70% of rated capacity, with more allowed after a load study. BESCOM's guideline of 5 August 2023 sets 80% for plants below 150 kW. Gujarat's 2024 amendment names no percentage. Check your own State Commission's current regulation, as several states have drafts under way.

What can I do if the DISCOM rejects feasibility because the transformer is full?

Ask for the reason and the figures in writing. Then choose from the official options: accept a lower capacity, stay in the queue (MSEDCL has a waiting-list option), ask for a load study where the regulation allows one, or ask for an upgrade, which rule 11(8) says the DISCOM or the consumer carries out.

Does the customer get compensation if the DISCOM delays feasibility?

Rule 11(12) of the Rights of Consumers Rules makes a DISCOM that delays without just cause liable to pay the consumer at least ₹500 for each day of default. The compensation is the consumer's, not the installer's, and a DISCOM may argue it had just cause, such as a full transformer. Keep dated letters showing when the due date passed.

Where do I complain if the DISCOM does not respond?

Go up in order: the sub-division's single point of contact, a written reminder quoting the rule, the PM Surya Ghar portal grievance route (30 days per the guidelines), the DISCOM's consumer grievance forum (rule 15: normally 30 days, not beyond 45), then the Ombudsman under section 42(6) of the Electricity Act, 2003. Each State Commission sets its own filing rules.

What does Feasibility Waived-off mean on the PM Surya Ghar portal?

MNRE's installer manual of 29 June 2024 shows stage 3 labelled Feasibility Waived-off in one screenshot, and neither manual defines the term. It fits the deemed rule for systems up to 10 kW, but confirm by opening the application, reading the Feasibility Approved by and Remarks fields, and downloading the Feasibility Letter if the portal shows one.

Want to put this into practice?

Quickest Solar CRM gives you everything in this article, proposal automation, lead capture, WhatsApp follow-up, built for Indian solar EPCs.

Start free

Get the next post in your inbox.

One email a fortnight. Real solar sales benchmarks. Unsubscribe anytime.