What is feasibility clearance?
Feasibility clearance is the DISCOM's confirmation that a proposed solar plant can be connected to the local distribution grid without causing voltage, reliability, or capacity issues. It is the first regulatory milestone in the net metering and grid connection process: the DISCOM technical team reviews the proposal, checks distribution transformer capacity, voltage limits, and protection compatibility, and issues clearance to proceed with installation. For a closer look at how this plays out in practice, see the DISCOM's step-by-step review workflow.
For residential rooftop under PM Surya Ghar, feasibility is integrated into the national portal flow, and applicants can track the national portal's integrated approval flow from application to clearance. For commercial and HT-connected projects, the DISCOM's net metering or interconnection cell handles applications through state-specific portals or offline submission. State-level processes vary substantially: some DISCOMs have online tracking; others require physical document submission.
Feasibility clearance is distinct from net metering approval. Feasibility is the entry permit confirming the proposed project can be installed; up to 10 kW the central Rules deem it accepted when the application is complete. After installation, a separate net metering application is filed for meter installation and operational approval.
Why feasibility clearance matters
For solar EPCs, feasibility clearance determines whether a customer order can be fulfilled. Above 10 kW, a denied or delayed feasibility can block the project (up to 10 kW a complete application is deemed accepted). Quality EPCs check distribution transformer capacity informally before customer commitment for marginal cases.
For customers, feasibility clearance is the regulatory assurance that solar generation will not create downstream issues. PM Surya Ghar subsidy is processed only after the DISCOM's inspection and approval on the national portal (MNRE CFA guidelines, July 2025, clause 6(k)), so a delay upstream cascades.
For DISCOMs, feasibility clearance protects grid integrity. High solar penetration in particular distribution areas can cause voltage rise during peak generation and reverse power flow issues. Feasibility check is the gatekeeping that prevents these issues.
How feasibility clearance is obtained
- Site survey. EPC confirms roof area, structure, electrical service.
- Sanction load check. Verify proposed solar within sanction limits.
- Single line diagram preparation. EPC prepares a single line diagram showing the electrical layout.
- Documentation compilation. Bills, ownership, vendor declaration.
- Application submission. Online portal or DISCOM office.
- Fee payment. Where applicable.
- DISCOM review. Technical team assessment.
- Site verification. Optional, depending on DISCOM.
- Clearance issuance. Or conditional approval / denial.
- Installation proceeds. Based on clearance.
Benefits of disciplined feasibility process
- Regulatory compliance. Required before installation.
- Risk identification. Capacity and voltage issues surface early.
- Customer confidence. Approved permit reduces concern.
- Net metering pathway. Foundation for final approval.
- PM Surya Ghar subsidy flow. Required step for DBT.
- Insurance acceptability. Documented compliance.
- Project finance enablement. Lenders may require feasibility.
Limitations and challenges
Timeline variation. Some DISCOMs slower than others.
Documentation burden. Multi-step paperwork.
State-specific processes. No national standard.
Denial risk. Distribution capacity constraints in some areas.
Communication gaps. Application status not always transparent.
Feasibility clearance across major Indian DISCOMs
Rules below are taken from each regulator's own text (checked 31 October 2026); for state-by-state DISCOM approval timelines covering the full net metering process, see the linked breakdown.
| State / DISCOM | Rule on feasibility |
|---|---|
| All states (central rule) | Rights of Consumers Rules, rule 11, as amended 22 Feb 2024: up to 10 kW deemed accepted with no study; above 10 kW study and outcome within 15 days, else presumed feasible |
| Delhi (BSES, TPDDL) | Central rule applies. We could not open the DISCOMs' own checklists, so confirm timelines on their portals |
| Maharashtra (MSEDCL) | MERC Second Amendment, 2024 (29 Aug 2024): study within 15 days, else presumed feasible; up to 10 kW deemed accepted |
| Karnataka (BESCOM) | BESCOM Common SOP for distributed solar PV (file dated 17 Oct 2025): up to 150 kW deemed feasible; above 150 kW, approval or rejection within 10 working days of acknowledgement |
| Tamil Nadu (TNPDCL, earlier TANGEDCO) | Central rule applies. We found no feasibility timeline on the utility's undated FAQ |
| Gujarat (DGVCL, MGVCL, PGVCL, UGVCL) | GERC Fourth Amendment, 2024: up to 10 kW deemed accepted; otherwise field report within 10 days of the head-office letter. GERC's DRES Regulations, 2026, listed on GERC's site as notified 30 Oct 2026, repeal the 2016 rooftop regulations, so read the new text for current timelines |
| Telangana (TGSPDCL, TGNPDCL) | TGERC Regulation 1 of 2025 (15 Nov 2025): 15 working days, else deemed approved; up to 10 kWp deemed accepted |
| West Bengal (WBSEDCL) | WBERC Regulations, 2025 (31 Jul 2025): up to 10 kW deemed accepted; above 10 kW study in 15 days and outcome with quotation in 20 days, else deemed accepted |
| Uttar Pradesh (UPPCL discoms) | Central rule applies. We have not verified a UP-specific timeline; check the UPPCL portal |
| PM Surya Ghar national portal | MNRE guidelines (July 2025), clause 6(h): up to 10 kW deemed accepted; the portal tracker shows "Feasibility Approval" or "Feasibility Waived-off". Until the state operationalises this, upload feasibility documents wherever the state still asks |
Quick facts
| Issued by | Local DISCOM |
|---|---|
| Purpose | Grid technical acceptance of proposed solar |
| Timeline | Up to 10 kW: deemed accepted. Above 10 kW: 15 days under the central rule; state rules vary |
| Documents | SLD, electricity bill, ownership, specs |
| Fees | Set by each state, e.g. Rs 2,500 for LT in Telangana, Rs 1,000 for LV and MV in West Bengal |
| Next step | Installation, then net metering application |
| Authority | Rights of Consumers Rules, State Commission regulations, CEA technical standards |
Common mistakes about feasibility clearance
- Starting installation before clearance or deemed acceptance. Compliance violation.
- Wrong sanction load assumption. Triggers denial.
- Incomplete documentation. Delays processing.
- Wrong SLD specifications. Technical rejection.
- Skipping site verification. DISCOM requests redo.
- No follow-up. Application stalls.
- Assuming national standard. State-specific patterns.
- Mixing with net metering approval. Different steps.
Key takeaways
- Feasibility clearance is DISCOM's technical OK for solar grid connection.
- First regulatory step before installation (waived by deemed acceptance up to 10 kW).
- Up to 10 kW a complete application is deemed accepted; above 10 kW the central limit is 15 days, with state rules varying.
- Documents include SLD, bills, ownership, plant specs.
- State-specific processes; PM Surya Ghar integrates flow nationally.
- Distinct from net metering approval (post-installation).
- Required for subsidy disbursement and project finance.
Frequently Asked Questions
What is feasibility clearance for solar?
Feasibility clearance (also called technical feasibility approval) is the DISCOM's confirmation that a proposed solar plant can be connected to the local grid without causing voltage, reliability, or capacity issues. It is the first regulatory step in the net metering and grid connection process. Up to 10 kW, a complete application is deemed accepted without a feasibility study; above 10 kW, installation follows the feasibility outcome, or the deemed approval if the DISCOM misses the 15-day limit (Electricity (Rights of Consumers) Rules, 2020, rule 11, as amended on 22 Feb 2024).
Who issues feasibility clearance?
The DISCOM (Distribution Company) for the local service area. Examples: BSES and TPDDL in Delhi, MSEDCL in Maharashtra, BESCOM in Karnataka, TNPDCL (earlier TANGEDCO) in Tamil Nadu, UPPCL in Uttar Pradesh. Each State Commission and DISCOM sets its own application process, within the central rules.
What does feasibility clearance check?
Whether the local distribution transformer has spare capacity to absorb solar generation, whether the LT or HT network can handle reverse power flow, whether voltage limits will be respected, whether protection schemes are compatible. For larger projects, full power flow study may be required.
How long does feasibility clearance take?
Set by each State Commission within the central limit. Under rule 11 of the Electricity (Rights of Consumers) Rules, 2020, as amended on 22 Feb 2024 (G.S.R. 125(E)), rooftop solar applications up to 10 kW, complete in all respects, are deemed accepted without a feasibility study. Above 10 kW the study must be completed and the outcome intimated within 15 days, failing which the proposal is presumed technically feasible. The Rules define days as clear working days. State examples: Maharashtra 15 days (MERC Second Amendment, 2024), Telangana 15 working days (TGERC Regulation 1 of 2025), West Bengal 15 days for the study and 20 days for the outcome and quotation above 10 kW (WBERC Regulations, 2025). HT and utility-scale projects follow the state regulation and the DISCOM's own procedure; no single national figure applies.
What documents are required?
Application form, site address proof, electricity bill, single line diagram (SLD), proposed plant specifications (kWp, modules, inverter) — see <a href="https://heavendesigns.in/blog/how-to-read-solar-single-line-diagram/" target="_blank" rel="noopener">how to read a solar single line diagram</a> for what this document must show — photo of proposed installation area, structural certificate where required, vendor declaration, drawing on <a href="https://heavendesigns.in/blog/solar-structural-engineering-in-india/" target="_blank" rel="noopener">structural engineering requirements for Indian rooftop solar</a>, and authorisation letter where applicable.
Is feasibility clearance the same as net metering approval?
No. Feasibility clearance is the initial technical OK to proceed. After installation, a separate net metering application is filed for net meter installation and final approval. Feasibility is the entry permit; net metering approval is the operating permit.
What happens if feasibility is denied?
Common reasons: distribution transformer at capacity, voltage stability concerns, protection scheme conflict. Projects are most often <a href="/blog/net-metering-rejection-reasons">denied for capacity or voltage-stability reasons</a>. Options: reduce project size, wait for DISCOM grid upgrade, propose grid-side improvements at developer cost, choose different connection point. Resubmission with modifications is allowed.
Is there a feasibility fee?
Set by each state, so there is no single national figure. Examples from regulator texts: Telangana (TGERC Regulation 1 of 2025, 15 Nov 2025) charges a processing fee of Rs 2,500 for LT and Rs 15,000 for HT per connection with the application. West Bengal (WBERC Regulations, 2025) charges a non-refundable Rs 1,000 for LV and MV and Rs 5,000 for HV and EHV, with government-funded schemes exempted under WBSEDCL Procedure-C (2025). Fees change with the regulations, so confirm on the DISCOM portal before quoting a customer.
Does feasibility apply to off-grid?
No. Off-grid systems do not connect to DISCOM grid and do not require feasibility clearance. However state inspector approval (CEI sanction) may still be required for safety compliance.
What is sanction load and how does it affect feasibility?
Sanction load is the maximum load the consumer is authorised to draw. For net metering, sanction load typically caps the maximum solar capacity that can be approved (for example, Telangana's 2025 regulation allows up to 100 percent of sanctioned load for residential and government consumers and 80 percent of sanctioned load or contract demand for industrial, commercial and others; other states differ). Feasibility check verifies proposed solar capacity is within limits.
Can feasibility be obtained before customer order?
Yes, and quality EPCs do this for marginal projects to confirm grid acceptance before committing the customer. For straightforward projects within DISCOM norms, feasibility is filed after customer order.
What is the role of CEI sanction?
Chief Electrical Inspector (CEI) sanction is separate from DISCOM feasibility. CEI verifies electrical safety compliance for installations above the capacity or voltage the state has notified under the CEA Safety Regulations, 2023; below that, the owner self-certifies. Both clearances may be required: DISCOM for grid acceptance, CEI for safety.
Run your solar business on Quickest Solar CRM
India's mobile-first solar CRM. Send subsidy-ready proposals on WhatsApp in 60 seconds. Free for 10 proposals a month, no card.
Start free →Sources
- State DISCOM net metering portals. Application process and timelines.
- CEA Technical Standards for Connectivity. Grid connection norms. cea.nic.in
- SERC regulations. State-specific net metering rules.
- MNRE solar rooftop guidelines. mnre.gov.in
- PM Surya Ghar portal. Standardised feasibility flow. pmsuryaghar.gov.in
- Electricity (Rights of Consumers) Amendment Rules, 2024. Rule 11, G.S.R. 125(E), 22 Feb 2024. Gazette copy
- State regulations cited in the table. MERC (2024), TGERC (2025), WBERC (2025), GERC, BESCOM Common SOP
- Forum of Indian Regulators publications. Best practice frameworks.
Written by Parth Maru, Sales & Operations Lead, Quickest Solar CRM (Surat).
Last updated: 31 October 2026.