A hybrid solar quote needs three separate answers: how much solar the roof can produce, which loads must work during a grid outage, and how long the battery should support them. A panel capacity and a battery size printed beside one price do not answer those questions. List the backed-up circuits, inverter operating mode, usable battery energy, assumptions for backup duration, connection and installation scope, and the events that end backup. Then price each component and test the finished proposal against the customer's actual load.

If the job is an eligible residential subsidy project, the DCR versus non-DCR quotation guide explains how to document module eligibility without treating battery backup as automatically covered.

This guide is for an Indian installer preparing a new hybrid system. It shows how to make a quotation with separate inverter, battery and backup-load lines. A battery upsell to an existing solar customer is a different decision. Here the task is to build the original quote correctly, then present it through a clear quotation-system workflow.

Technical sources checked: 23 November 2026. The Central Electricity Authority's 2023 safety regulations and the current utility requirements govern the actual installation. A 2026 CEA battery-safety amendment found during research says it will come into force on 1 April 2027, so it is not treated here as a rule already in force. A qualified designer must confirm the equipment, protection and local approval path. CEA safety regulations register; 2026 amendment text.

Ask what “backup” means to this customer

Customers often say they want “the whole house on battery” without listing what they actually use during an outage. Start with the tasks: lights, fans, refrigerator, Wi-Fi, water pump, medical equipment, office computer or a particular machine. Ask which must run at the same time, which starts with a surge, and which can wait. Ask whether the target is one hour, an evening, or through a long outage. The answer decides the critical-load panel and battery design.

Do not infer the need from the monthly bill alone. A monthly kWh total does not say which devices are on when the grid fails. Walk the site and record nameplate ratings, actual measured consumption where possible, starting behaviour and phase. A pump with a modest running draw may have a start requirement that an undersized inverter cannot serve. The customer's phrase “5 kW backup” may refer to inverter power, not stored energy. Explain the difference before entering a price.

Separate power from energy in the proposal. Kilowatts (kW) describe the instantaneous load the inverter must supply. Kilowatt-hours (kWh) describe energy over time. A battery with a 10 kWh nameplate and an inverter rated at 2 kW cannot necessarily start a 3 kW motor. An inverter rated at 5 kW with too little usable battery energy may run a 1 kW load for less time than the buyer expects. A quote that states only “5 kW hybrid system” is ambiguous about both.

Ask how the customer expects the system to behave when the grid returns. Should the battery keep a reserve, charge from solar, charge from grid, or follow a scheduled mode? Which circuits should stay on during changeover? What transition time can the connected devices tolerate? Use the exact proposed inverter and battery documentation to answer. Do not promise “uninterrupted” operation from a generic hybrid label.

Build a critical-load schedule first

Make one table for the loads the customer wants backed up. Record quantity, measured or justified running watts, starting power if relevant, hours needed and whether simultaneous use is expected. Ask the customer to sign off the list. A document that names the circuits prevents a later argument that every socket was included.

Load or circuitQuantityRunning power basisStarting or surge issueHours requestedIncluded in backup?
Essential lightingSite countLamp ratings or measured circuitUsually small, verify driver behaviourCustomer inputYes/no
Fans or ventilationSite countNameplate or measured drawMotor start to checkCustomer inputYes/no
Refrigerator or cold roomExact applianceMeasured or manufacturer dataCompressor start to checkCustomer inputYes/no
PumpExact motor and phaseRated and measured drawHigh start demand possibleCustomer inputYes/no
Other critical equipmentExact itemManufacturer data and site checkEquipment-specificCustomer inputYes/no

Do not put a fictional household into the public quote template. The table above is a worksheet structure; real values belong to the customer's job. When measurement is unavailable, mark the assumption and a verification action. The installer must not silently use a typical wattage from an old brochure for a medical device or a motor.

The sum of simultaneously running loads is an initial inverter power requirement, not the final selection. Check starts, power factor, phase, surge duration and the manufacturer's approved operating conditions. A designer may split the critical circuits or change the load list rather than buying a larger inverter. The quotation should state which solution is included and what would require a revision.

Calculate battery energy with visible assumptions

Begin with each backed-up load's energy: running kW × hours = kWh. Add the loads that operate during the target backup period. Adjust for inverter and wiring losses, usable battery capacity, battery management limits, temperature, aging and the reserve the customer wants to retain. Use the exact battery and inverter datasheets for the final figures. The Government of India's rooftop PV training material teaches battery sizing from load energy, system efficiency and depth of discharge. Directorate General of Training rooftop PV workbook.

An illustrative calculation makes the units clear. Suppose the approved backed-up load averages 1.5 kW for four hours. The AC energy requirement is 1.5 × 4 = 6 kWh. If a hypothetical system delivers 90% of battery energy as usable AC energy and permits 80% of nameplate battery energy to be used under the chosen reserve policy, the rough nameplate requirement is 6 ÷ (0.90 × 0.80) = 8.33 kWh. Those 90% and 80% factors are teaching assumptions, not a specification for a real product. The final design may need more capacity for starting loads, discharge rate, temperature, aging, warranty limits or a longer outage.

Calculation itemIllustrative inputFormula or resultFinal quote must use
Average critical load1.5 kWMeasured/approved loadsCustomer's critical-load schedule
Required time4 hoursCustomer's chosen durationWritten operating scenario
AC energy6 kWh1.5 kW × 4 hCircuit-by-circuit energy
Conversion factor0.90HypotheticalExact inverter/system data
Usable fraction0.80HypotheticalBattery data and reserve setting
Nameplate estimate8.33 kWh6 ÷ (0.90 × 0.80)Engineered capacity and model

A battery's nameplate energy is not the same as its guaranteed delivered energy at the socket. A warranty may limit depth of discharge or throughput, and usable capacity can change with conditions. A fixed “four hours backup” claim should be linked to the stated load list, battery state of charge at outage start, operating mode and test conditions. Without those, present an estimate and a test plan, not a guarantee.

Specify the hybrid inverter as an exact product

A quote must name the inverter manufacturer, model, AC rating, phase, number of units, solar input limits, battery compatibility and supported operating modes. The selection must follow the current datasheet and installation manual. Do not write “5 kW hybrid inverter or equivalent” when the battery, grid export, backup circuit and monitoring depend on model-specific controls. If substitution is allowed, require a technical and commercial review before installation.

Ask whether the proposed system is grid-connected with backup, off-grid with grid support, or another manufacturer-defined mode. Confirm what happens during a grid outage, whether solar can charge the battery while islanded, and how it returns to grid operation. Confirm the utility's permission for the specific connection and export arrangement. A generic on-grid quote with a battery line added at the bottom is not a hybrid design.

Show where the critical-load distribution board, changeover device, isolation, protection, metering and monitoring sit. A one-line diagram or a simple labelled diagram should accompany a serious quote. The diagram should mark the grid, PV, inverter, battery, critical loads and ordinary loads. It must not suggest a backup connection to ordinary circuits that were not engineered for it. Use a qualified electrical designer for the final drawing and approvals.

Battery chemistry, enclosure, ventilation, clearances, temperature range and fire provisions must come from the selected equipment and current safety requirements. The CEA has issued safety regulations and a future-dated battery amendment; the date matters. Do not claim compliance by citing a future rule before it takes effect. The quote should name the review and the installation deliverables, not make a blanket “fully certified” assertion without product evidence. CEA safety regulations.

Keep the solar array and backup promise separate

PV array size is a generation design. Battery size is a storage design. They interact, but they are not the same number. Calculate the PV array from roof space, shading, module/inverter limits, daytime demand and the customer's bill objective. Calculate the backup from the critical-load schedule and required duration. Then check whether the array can recharge the battery under realistic conditions and whether grid charging is permitted or desired. State what happens after consecutive cloudy days and repeated outages.

A homeowner may assume that a 5 kW PV array always delivers 5 kW to loads and charges the battery at the same time. Explain that module nameplate capacity is measured under defined test conditions, while actual output changes with sunlight, temperature, shading and losses. If the quote includes an annual generation estimate, show its weather source, tilt, orientation, shading, loss assumptions and exclusions. Do not derive battery runtime from panel nameplate watts.

For a residential PM Surya Ghar application, check current scheme eligibility, module requirements, National Portal process and the utility's rules for the proposed configuration. A subsidy amount must be shown as conditional and separate from the contract price. A hybrid label does not prove the customer or system qualifies. The current scheme guidance is on MNRE's rooftop programme page and operational guidelines. MNRE rooftop programme.

Do not add a “solar runs your home 24/7” line. During a long outage, stored energy may be exhausted; at night there is no PV generation. The right promise is a defined load and operating scenario. Tell the buyer how to reduce loads when the battery state of charge falls and what alarm or monitoring they will see.

Make the price schedule match the design

Give the buyer a line-by-line bill of materials. Include PV modules, mounting and roof work, hybrid inverter, battery modules and battery management system, enclosure and protection, critical-load board, changeover, cables, meter or utility work, installation, testing, commissioning and handover. Add any required civil work or monitoring service. If a line is excluded, say who will supply it and whether the system can work without it.

Quote lineMinimum detailCommon omission to catch
PV modulesExact maker/model, wattage, count, DC kWpSubstitution without revised design
Hybrid inverterExact model, phase, AC power, supported modesSurge and battery compatibility
BatteryChemistry, model, nameplate/usable energy, quantityCalling nameplate kWh “backup hours”
Critical-load boardCircuits included, protection and changeoverAssuming every socket is backed up
Balance of systemCable, protection, mounting and meteringMissing accessories needed for commissioning
ServicesSurvey, design, installation, utility process, tests, trainingNo acceptance criteria or handover
Warranty and maintenanceSeparate OEM and installer termsOne vague “full warranty”

The quotation needs the actual supplier price, freight, labour and approved tax treatment for each supply. A solar goods rate is not automatically the rate for every installation service or bundled contract. Leave tax input editable until a qualified reviewer checks the current notification and supply structure. Do not show an invented market battery price or a payback calculation based on it.

List the payment milestones and the test that releases each one. A final payment “after completion” is ambiguous if the utility connection or backup test is pending. Define a commissioning checklist: verify correct wiring and protection, normal grid operation, outage/transfer mode under a safe test plan, critical-load supply, battery charge/discharge and monitoring handover. The customer and installer should agree the test load and conditions before calling the quoted backup duration accepted.

Present two operating scenarios to the customer

A clear proposal has a normal-day scenario and an outage scenario. On a normal day, explain whether PV serves site loads, charges the battery, exports where permitted, or is curtailed. During an outage, identify the critical-load circuits, the role of PV, the battery's minimum state of charge, the expected load and what ends the backup. A simple flow diagram can help, but the same facts must appear in text for a reader on a phone or in an accessible PDF.

Show the trade-off between more battery capacity and a tighter critical-load list. Sometimes the cost-effective response is to back up fewer devices well. Sometimes the customer has a real need for a longer duration and the extra storage, controls and space are justified. Do not select the cheapest battery merely to hit a budget while leaving the promised load unchanged. Equally, do not sell a large battery without checking whether the buyer's outages and goals warrant it.

Before sending, have a second person read the quote. Can they find the exact backed-up loads, inverter and battery models, usable energy assumption, duration scenario, tax and subsidy treatment, exclusions and acceptance test? Can they tell whether the system will work during a grid outage and which circuits will remain off? If not, revise the document. A price table alone is not a hybrid proposal.

Quickest Solar CRM can produce a branded quotation PDF with your logo, items and terms, and share it on WhatsApp, as described in its product offer. Use the backed-up load schedule and item table above when preparing the quote. See the quotation-system page for the product workflow. The app presents your verified inputs; it does not size a battery or certify an electrical design. You can create a Quickest account and inspect the PDF before sending it to the customer.

For a document with separate PV, battery and backup-scope fields, use the hybrid solar quotation format. Replace every illustrative value with the measured loads, selected equipment and reviewed tax treatment for the actual job.

The next job is practical: get the critical-load list, collect equipment documents, confirm the utility and safety path, calculate power and usable energy separately, and put the operating states on the quote. That turns “battery backup” from a vague sales line into a deliverable the customer can inspect and test.

Want to put this into practice?

Keep your solar leads, proposal documents and follow-up tasks in one workflow.

Create account

Get the next post in your inbox.

Get practical guides for solar sales and proposals. Unsubscribe anytime.