Before a commercial solar site visit, check whether there is a real buyer, usable connection, roof right, energy need and decision path. A company name and a large roof are not enough. The quickest useful qualification is a short conversation plus a request for the recent electricity bills, site location, roof ownership and the people who must approve the project. If those are missing, record what is unknown and agree a next step before committing engineering time to a detailed proposal.

For the earlier prospecting step, see how to find commercial solar leads without treating an unverified contact list as a pipeline.

This guide gives an EPC ten checks to make before a C&I quotation. It is not a rigid score that declares a customer good or bad. A project can be promising but temporarily blocked by a roof lease or a finance decision. A lead can look attractive on annual electricity spend yet fail because the proposed roof belongs to another party. The point is to know which fact must be resolved before a technical team designs a plant.

Use the checklist below as the information contract between sales and engineering. The general solar lead qualification guide covers broader sales questions; this page focuses on C&I bill, roof, connection and buying-committee issues.

The ten checks at a glance

CheckAsk or obtainWhat a good next step looks like
1. Site and buyer identityLegal customer, site address, electricity-account holderConfirm who may approve a survey and contract
2. Energy objectiveBill reduction, resilience, budget, compliance or expansion goalRecord the buyer's priority in their words
3. Bill and tariffRecent bills, connection category, demand and energy chargesFinance/engineering identifies usable data and gaps
4. Load timingOperating hours and interval data if availableEstimate likely self-consumption only after analysis
5. Roof rightsOwner, tenant, lease term and written access pathObtain permission to inspect and install if feasible
6. Roof conditionAge, type, structure records, obstructions and safetySchedule technical/structural review, not a blind price
7. Electrical interfaceMeter, transformer/panel, sanctioned load and outage limitsEngineer scopes interconnection study
8. Commercial modelCAPEX ownership, financing or OPEX/PPA interestSelect the right proposal and contract path
9. Decision chainTechnical, finance, procurement, owner and legal reviewersAgree who attends the next meeting
10. Timing and next commitmentBudget window, target date and missing approvalsName owner/date for the next evidence or decision

The table is a workflow, not a compliance certificate. A sales rep should not interpret a roof photograph as structural approval or a bill total as a financial model. The right next step may be a bill review, a site survey, a landlord call or a polite decision to defer. Each outcome is useful when recorded accurately.

1. Identify the customer and the site

Ask which legal entity will buy the EPC service or sign the PPA, which entity pays the electricity bill, who owns the building and whether the site has multiple connections. A company may operate in a leased factory while a different entity owns the roof. A campus may have several meters and one common roof. If you build the proposal around the wrong party, the installation right or billing model may not work.

Record the exact site address and utility account reference with appropriate permission. Do not ask for sensitive data you cannot protect or do not need at this stage. For an early call, the utility name, consumer category and approximate bill may be enough to decide whether a deeper conversation is worthwhile. Before an engineering quote, the actual bill and connection details become necessary. Separate “lead identified” from “facts verified” in the record.

Ask who can authorize access for the survey. The plant may cross roof areas, electrical rooms or production zones controlled by different people. If the first contact cannot give access, ask for an introduction rather than treating silence as approval. A site visit arranged without the right permission can waste the customer's and EPC's time.

2. Learn the business objective

“We want solar” is a start, not a requirement. Ask why now. Has the electricity bill changed, is a new facility being built, is there an internal capital budget, or does the company have an energy target? The answer affects what the first proposal should show. A buyer interested in predictable operating cost may need a different comparison from one focused on ownership and tax planning.

Ask what would make the project unacceptable. Perhaps the factory cannot interrupt a line, the owner refuses roof penetrations, the tenant cannot commit beyond its lease, or the board requires a particular payback threshold. Do not agree to a threshold before seeing the bill and design. Record it as a decision criterion, then show what assumptions the financial model would need to test it.

The reason for the project also tells you whom to involve. A facilities-led enquiry may need finance early. A finance-led enquiry may need roof and electrical engineering before it can trust the return estimate. When the first meeting concludes, repeat the buyer's objective back to them. If you cannot state it clearly, the lead is not ready for a detailed proposal.

3. Read the actual bill

Request a run of recent bills, ideally enough to see seasonality, rather than one photograph of the amount due. Capture units, tariff category, sanctioned or contract demand, billing demand, fixed and energy charges, time bands if present, and any adjustments that matter. The question is not merely “How many rupees do you pay?” The EPC needs to know which units solar can displace, when they are used and which bill components may remain.

Do not multiply an estimated annual solar generation number by the highest visible rupee-per-unit line and call the result savings. Some charges may not vary with rooftop output. Export treatment depends on the applicable metering arrangement and state rule. A reliable model needs the site-specific bill and current utility/regulatory basis. The CEA publishes current safety and electric-supply regulations, and state commissions publish local rooftop rules; identify the applicable jurisdiction before promising a connection outcome. CEA regulations index.

If the customer will not share bills yet, you can still qualify their interest and arrange a confidentiality process if needed. Mark the financial estimate as pending. Do not invent a “typical factory bill” in the actual quote. The missing bill is a stage gate, not a reason to guess.

4. Understand when the site uses electricity

Annual units alone hide daily and weekly patterns. Ask about operating shifts, weekends, planned shutdowns, seasonal production, refrigeration or air-conditioning load, and future equipment. Interval data can improve the self-consumption estimate. If it is unavailable, state the limitation and avoid a precise claim about how much output will be used on site.

A business that operates mainly at night may still be a potential solar buyer under the right arrangement, but the value calculation differs from a daytime load. Do not disqualify it from a phone call based on one rough assumption. Ask an engineer to model the relevant connection and use profile after the customer permits the data review.

Record planned expansion separately from current load. A factory may expect new machinery, but a planned load is not yet an observed bill. Show scenarios if the future is uncertain. A roof layout and inverter choice built for an unapproved expansion can produce an oversized project for today's demand.

5. Check roof rights before roof area

Who owns the roof, and who can grant installation, access and maintenance rights for the intended term? A tenant may need landlord consent. A multi-tenant building may have common-area or association approvals. A RESCO/PPA developer may need long-term rights beyond a simple site visit. Ask for the relevant decision path and document, then let legal counsel review the actual right before a binding offer.

Do not treat a verbal “roof is ours” as final evidence if the company and property owner differ. Similarly, do not promise the customer that a project is impossible because the roof is leased; an agreement might be possible. The qualification outcome is “roof permission needed,” with an owner and date. This is a better pipeline status than “unqualified” or “proposal sent”.

The roof also has operational rights: access hours, lifting, safety zones, waterproofing and future maintenance. These should become scope inputs. A cheap quotation that ignores access costs may be difficult to execute even when the roof itself is large.

6. Identify physical and structural constraints

Ask the roof type, age, drawings, prior repairs, water ingress, obstructions, shade sources and safe access. An industrial shed may have a large visible surface but a roof structure that needs engineering review. A concrete roof may have equipment and walkways that reduce usable area. Do not calculate capacity from gross area without considering these constraints.

The salesperson can collect photographs and drawings with the owner's permission. The technical team should assess the design. If a structural assessment is required, say whether the EPC includes it, the customer provides it, or a specialist is separately engaged. Do not ask a sales rep to certify load capacity. When the result is uncertain, send a budget range and survey plan rather than a fixed installed price.

Check the work environment. Can the roof be accessed without disrupting operations? Are there hazardous areas, height restrictions or no-go zones? Will installation require a shutdown or special permit? These details affect safety, schedule and cost. They should be answered before the EPC commits to an installation method.

7. Examine the electrical interface

Ask for the relevant single-line diagram if available, connection and meter details, sanctioned load, main panel information, transformer details if applicable, and planned changes to the electrical system. The engineer can then assess the proposed point of connection and protection. A 100 kWp sales target does not establish that the existing interface can accept the design.

Record the utility and state. Rooftop capacity, net/gross metering, approval process and charges are subject to current rules. Do not copy an eligibility limit from another state into the proposal. If the site is in Gujarat, consult current GERC regulations and the distribution licensee's process; if elsewhere, use that jurisdiction's primary sources. GERC regulations index illustrates why an old base regulation must be read with amendments.

Ask about shutdown constraints. A hospital or continuous-process factory may need a planned isolation window. The technical team must decide the method; sales only needs to learn that the constraint exists so the initial quote does not assume unrestricted access.

8. Select a commercial model the buyer can authorize

Does the business want to own the system under an EPC CAPEX purchase, finance it, or buy solar output under an OPEX/RESCO PPA? This decision changes the proposal, legal parties and risk allocation. Do not call an OPEX offer “no-cost solar” without explaining the long-term payment and roof obligations. Do not compare a CAPEX total with an OPEX per-kWh tariff as if they were the same unit.

Ask whether the buyer has a capital budget and who approves it. If a third-party developer is involved, identify that entity and its due-diligence requirements. The EPC may only be a construction provider. For qualification, find which ownership model deserves a detailed proposal and which terms remain unresolved.

Do not assume central residential PM Surya Ghar assistance applies to a C&I buyer. MNRE's guidelines for that assistance component explicitly exclude non-residential customers. If the buyer asks about another incentive, assign a primary-source check before it enters a quote. MNRE operational guidelines.

9. Map the decision chain

Ask who will approve the technical design, budget, contract, roof access and purchase order. These may be five people, one owner or a formal committee. Name the roles even before you have every person's contact. A proposal that reaches only the facilities manager may stall if finance was never included. A finance-only proposal may stall because the plant cannot be built on the roof as assumed.

Ask the first contact how the company compares vendors and when it expects to decide. Do they need a standard bid format, multiple quotations or a board note? Who reviews warranties and maintenance? If procurement has mandatory terms, get them before drafting your own agreement. Respect the buyer's process rather than repeatedly calling the first person for an answer they cannot give.

At the end of the first meeting, agree who will join the technical call and who will provide the bill and roof documents. Put those names and dates in the pipeline. This is a concrete advance in qualification, even when no price has been discussed.

10. Choose the right next deliverable

Not every qualified enquiry needs a full EPC quotation tomorrow. If bills are available but roof rights are not, the next deliverable may be a feasibility conversation with the landlord. If the site is clear but the financial model is undecided, the next deliverable may be a CAPEX/OPEX comparison. If the buyer has a formal tender, the next step may be a bid/no-bid decision and document review. If the roof is structurally uncertain, a survey and engineering brief come first.

Use three statuses in your team: ready for detailed quote, promising but blocked by named evidence, and not a fit for the current offer. The middle status needs an owner and date. “Follow up later” without the missing fact is not a plan. A good CRM note says, for example, “Roof-owner letter pending; buyer to share by [date]; engineer will review shed drawing after receipt.”

Quickest Solar CRM includes customisable lead stages and labels, team permissions and follow-up reminders. Those can help a team track this process, but the product does not validate roof rights or engineering inputs for you. Quickest's commercial proposal workflow can be tested with a representative project during a demo. To examine a real quote and follow-up workflow, start free and check the current app before using it with a client.

A pre-visit handoff for sales and engineering

Before sending an engineer to the site, prepare a one-page brief: customer and address, connection, bills received, load pattern, roof owner, drawings/photos, access contact, suspected constraints, commercial model, decision makers and what the visit must resolve. Mark unknowns. The engineer can then plan measurements and questions, and the customer sees that the visit has a purpose.

After the visit, update the same brief with confirmed facts, new risks and the next deliverable. If the project scope changes, tell the buyer before making a price promise. The sales rep should not keep quoting the original capacity after engineering reduces the usable area or identifies extra electrical work.

A qualified lead is one where the EPC knows enough to choose a responsible next step. It need not be perfect or ready to sign. It must have a buyer, a project question, evidence to examine and a path to a decision. That is the standard worth meeting before a detailed commercial solar quote consumes your team's time.

Want to put this into practice?