The PM Surya Ghar portal has nine steps across two user roles, the consumer and the installer. Most installers know the customer-side flow vaguely but trip up on the installer-side submission: wrong photo format, missing serial numbers, or submitting before the DISCOM inspection is scheduled. One error at any step delays the project by 2–4 weeks.

This guide walks through every step in order, from the customer's first portal registration to the installer's commissioning report upload, with the exact documents and common errors to avoid.

Key takeaway

PM Surya Ghar application has nine steps, steps 1–4 are consumer-led, steps 5–7 are installer-led. Total timeline: 45–90 days. The two biggest installer-side errors are submitting the commissioning report without GPS-tagged photos and using non-ALMM equipment. Either error results in DISCOM rejection and a restart of steps 6–7.

The entire process runs through the PM Surya Ghar national portal, both consumer-facing and vendor-facing modules. The MNRE provides the technical guidelines, but the DISCOM (Distribution Company) is the operational gatekeeper at every approval step.

Before You Start, The Prerequisite Checklist

Before the customer registers on the portal, confirm these prerequisites are in place:

Prerequisite Consumer Installer
Active DISCOM electricity connection (domestic category)✓ Required-
Aadhaar-linked bank account✓ Required for DBT-
DISCOM empanelment on national portal-✓ Required
ALMM-listed module and inverter models selected-✓ Required
MSME / Udyam registration-✓ Required for empanelment

Steps 1–4, The Consumer Side

Your job during Steps 1–4 is to guide the customer through the portal, not do it for them. The customer must complete registration with their own Aadhaar OTP. You can sit beside them or share your screen to walk through.

Step 1, Consumer registration on the portal

The customer visits pmsuryaghar.gov.in and clicks "Apply for rooftop solar."

  • Enter mobile number → receive OTP → create account
  • Fill in: name, state, DISCOM name, electricity consumer number from the bill
  • The portal validates the consumer number against the DISCOM's database, if the number is wrong, registration fails

Common errors:

  • Consumer number entered with extra spaces or dashes, enter exactly as it appears on the bill
  • Wrong DISCOM selected, in areas served by multiple DISCOMs (like Delhi or UP), check the bill header carefully

Step 2, Apply for net metering / feasibility

After registration, the customer submits an application for net metering feasibility approval.

  • Select: rooftop solar application type
  • Enter desired system capacity (kW)
  • Upload: recent electricity bill (PDF or photo), ID proof (Aadhaar), property ownership proof

The DISCOM receives this application through the portal and assigns it to a technical officer. The officer checks whether the local feeder (transformer) has capacity for solar injection.

Step 3, DISCOM feasibility approval

This is the first wait period: 7–15 working days in most DISCOMs, up to 25 days in slower ones.

The DISCOM either:

  • Grants a feasibility letter with the sanctioned capacity (e.g., "3 kW approved"), proceed to Step 4
  • Requests additional documents (wiring diagram, site photo), customer submits and waits again
  • Rejects (feeder overloaded), customer is notified; your project is blocked until feeder is upgraded

Step 4, Consumer selects installer

Once feasibility is approved, the consumer's portal dashboard shows a list of DISCOM-empanelled installers in their area. The customer selects you (or is advised by you to select your company).

This is why empanelment is critical: if you're not on this list, the customer cannot link you to their application.

Fast tip. Before your customer's feasibility approval arrives, confirm that your company name appears correctly on the portal's empanelment list for their DISCOM. Spelling mismatches between your company name in the portal and the customer's perception of your brand cause unnecessary confusion at installer selection.

Steps 5–7, The Installer Side

Once the customer selects you, the project appears in your vendor dashboard. Steps 5–7 are your responsibility.

Step 5, Complete the installation

Install the ALMM-listed system within the DISCOM-sanctioned capacity. Key rules:

  • Do not exceed the sanctioned capacity from the feasibility letter
  • Use exactly the modules and inverter models listed in your BOM submission, no mid-project substitutions
  • Record each module's serial number and the inverter's serial number before mounting
  • Take GPS-tagged photos: panels on roof (before wiring), complete system (after wiring), inverter installation, meter location

Note. GPS-tagged photos are mandatory, the portal requires photos with embedded GPS coordinates. Most Android phones GPS-tag photos automatically when location is enabled. Verify this is on before your installation team starts, re-photographing after mounting is possible but wastes time and sometimes requires panel dismounting.

Step 6, Submit the installation report on the portal

Log into the vendor dashboard and submit:

  • Module serial numbers (every panel)
  • Inverter serial number
  • GPS-tagged installation photos (4–8 photos minimum)
  • Commissioning certificate (issued by your company)
  • Single-line diagram of the system
  • Customer's confirmation of installation completion (digital signature or OTP)

After submission, the portal notifies the DISCOM for inspection scheduling.

Common errors that cause rejection:

  • Module serial numbers don't match the ALMM listing for that brand/model
  • Photos without GPS coordinates (taken with location services off)
  • Capacity installed exceeds the sanctioned capacity
  • Missing single-line diagram
  • Non-ALMM model installed (instant rejection)

Step 7, DISCOM inspection and net meter installation

The DISCOM schedules a technical officer visit. The officer:

  • Physically verifies the installation matches the commissioning report
  • Checks module model numbers against ALMM list
  • Approves the connection for bi-directional flow
  • Replaces the existing meter with a net meter

This inspection takes 15–30 days from commissioning report submission, depending on the DISCOM.

Watch out. Some DISCOMs schedule the net meter installation 30–60 days after commissioning approval. During this period, the system is technically installed but the customer cannot export power back to the grid. Alert your customer to this gap, don't let them assume the system is "done" just because installation is complete.

Step 8, Subsidy Disbursement (Consumer Action Required)

After DISCOM commissioning approval, the portal prompts the customer to submit bank account details for DBT. The customer must:

  • Log into their portal account
  • Confirm bank account number and IFSC linked to Aadhaar
  • Submit the DBT request

The central subsidy (and any state top-up) arrives in the customer's Aadhaar-linked account within 30 days of this submission in most states.

The Full Timeline, By DISCOM Type

Step Fast DISCOM (Gujarat) Average DISCOM (MH) Slow DISCOM (UP)
Registration → Feasibility approval7–10 days15–20 days20–30 days
Installer selection → Installation3–7 days5–10 days5–10 days
Commissioning report → DISCOM inspection10–15 days15–25 days25–40 days
Approval → Subsidy DBT15–20 days20–30 days25–40 days
Total typical range35–52 days55–85 days75–120 days

The Application Tracker, What Installers Should Monitor

Track these six status checkpoints in your project management system for every active PM Surya Ghar project:

  1. M0

    Consumer registered + feasibility submitted

    Confirm portal registration is complete and feasibility application is submitted to DISCOM.

  2. M1

    Feasibility approved, capacity confirmed

    Note the sanctioned kW. Do not procure or install more than this capacity.

  3. M2

    Installation completed

    GPS photos taken, serial numbers recorded. Commissioning report ready to submit.

  4. M3

    Commissioning report submitted on portal

    All documents uploaded. DISCOM notified. Inspection scheduled.

  5. M4

    DISCOM inspection passed + net meter installed

    System is live on the grid. Customer can start generating and exporting power.

  6. M5

    Subsidy DBT received by customer

    Follow up with customer to confirm receipt. Ask for referrals at peak satisfaction.

How QuickEstimate Tracks Every Active Application

Managing 10–20 active PM Surya Ghar applications simultaneously, each at a different milestone, with different DISCOM timelines, is where manual tracking breaks down completely.

  • Pipeline Management, Create a PM Surya Ghar pipeline with stages mapped to M0–M5 above. See every project's current stage at a glance. Move projects between stages with one tap as milestones complete.
  • WhatsApp Follow-up, Send automated status updates to customers at each milestone: "Your feasibility is approved, we're starting installation next week." Keeps customers informed without manual messages.
  • Sales Reports, Track how many projects are stuck at each milestone. If 8 out of 15 active projects are stuck at M3 (commissioning report submitted), you have a DISCOM inspection bottleneck, and data to escalate it.

The complete PM Surya Ghar guide covers the full scheme context if you need a refresher on eligibility and subsidy slabs before walking customers through the application.

What to Do This Week, For Your EPC

  1. Map your active PM Surya Ghar projects to the M0–M5 milestones. Identify which projects are stuck at which milestone and why. Unstick one stuck project per day this week.

  2. Create a commissioning report checklist. List every required document for a clean portal submission: GPS photos, serial numbers, single-line diagram, commissioning certificate. Laminate it and put it in every installation kit.

  3. Set a weekly reminder to check DISCOM inspection scheduling. The portal shows when inspections are scheduled. If a project has been at M3 for more than 20 days, follow up with the DISCOM officer, delayed inspections are the top cause of customer dissatisfaction.

Frequently asked questions

How long does the PM Surya Ghar portal application take?

The full process from consumer registration to subsidy disbursement takes 45–120 days depending on the DISCOM. Gujarat DISCOMs (DGVCL, UGVCL) typically complete in 35–52 days. Maharashtra (MSEDCL) averages 55–85 days. UP-based DISCOMs average 75–120 days. Delays usually occur at the feasibility approval step or the DISCOM inspection step.

Can I submit the PM Surya Ghar commissioning report on behalf of the customer?

No. The consumer must log into their portal account and complete the DBT bank account submission themselves. However, as the installer, you submit the commissioning report from your vendor account. The two submissions are linked to the same application, the consumer side and vendor side are separate portal modules.

What documents does the installer upload on the portal?

The installer uploads: GPS-tagged installation photos (minimum 4–8, with location metadata), individual module serial numbers, inverter serial number, a commissioning certificate, and a single-line system diagram. Some DISCOMs also require the BOM invoice showing ALMM-listed materials purchased.

What happens if the DISCOM inspection fails?

If the DISCOM inspector finds a discrepancy, wrong module model, wrong capacity, non-ALMM equipment, or missing wiring standard, the inspection is marked failed. You receive a rejection notice via the portal. You must correct the issue and resubmit for a new inspection. This restarts the 15–30 day inspection timeline.

Can the customer track the application status themselves?

Yes. The consumer's portal dashboard shows the current status of their application at every step, feasibility approval, installer assignment, installation verification, inspection, and subsidy disbursement. Train your customer to check this dashboard regularly and WhatsApp you when a new notification appears.

Want to put this into practice?

QuickEstimate gives you everything in this article, proposal automation, lead capture, WhatsApp follow-up, built for Indian solar EPCs.

Start free

Get the next post in your inbox.

One email a fortnight. Real solar sales benchmarks. Unsubscribe anytime.